You have purchased your land. What's next? From the building permit to project completion, here are all the steps to build in full compliance with the law.
Need a land expert?
Speak with an advisor for free. Response within 2 hours.
You have bought a plot of land. The ACD (Arrêté de Concession Définitive / Definitive Concession Decree) is in hand, the Titre Foncier (TF / Land Title) is registered, and the surveyor has marked the boundaries. You are impatient to start. A local mason offers to begin the foundations "while waiting for the permit."
Official timeline: according to Ivorian administrative texts, an ACD issued on an approved subdivision must be delivered within 180 calendar days to the MCLU (Ministry of Construction, Housing and Urban Planning), per the BÂTIR bulletin N°004 of 2022. In practice, 6 to 12 months often pass between filing and publication in the Land Registry, sometimes more, for reasons the administration does not always spell out. One point to keep in mind: the Titre Foncier is created by the Conservation de la Propriété Foncière et des Hypothèques (CPFH, the Land and Mortgage Registry) during the ACD procedure, at step 3, not after. The ACD published in the Land Registry is the TF published.
This is exactly what you must not do.
In Ivory Coast (Côte d'Ivoire), building without a permit is illegal. Unauthorized constructions can be demolished by the administration, with no compensation. And demolition is not the only risk: a building put up without a permit cannot obtain a certificate of conformity, which blocks any formal resale or rental.
This guide walks through each step, from the land prerequisites to the final certificate of conformity, so that you build within the law.
Before contacting an architect, check that your land file is complete.
| Document | Role | Where to obtain it |
|---|---|---|
| ACD or Titre Foncier | Proof of ownership | MCLU / Land Registry ([dgi.gouv.ci](https://www.dgi.gouv.ci)) |
| Approved subdivision | Confirms that the zone can be built on | MCLU ([construction.gouv.ci](https://www.construction.gouv.ci)) |
| Boundary survey report | Exact limits of the parcel | Licensed surveyor, OGECI |
If your land sits in an unapproved subdivision, no building permit can be issued. Check the status of the subdivision before running up architect fees.
Using an architect registered with the Ordre des Architectes de Côte d'Ivoire (OACI, the Ivorian order of architects) is mandatory for:
Below 150 m², the law does not require an architect. One is still useful: a badly assembled permit application comes straight back to you, and the time lost usually costs more than the fees saved.
Architect fees generally represent 8 to 12% of the total construction cost, split by phase.
| Phase | Share of fees |
|---|---|
| Sketch and preliminary studies | 2 to 3% |
| Detailed preliminary design | 3 to 4% |
| Execution and site supervision | 3 to 5% |
The architect and the technical engineering firms produce the complete file. The architectural plans cover the floor levels, the elevations, the sections, and the way the building sits on its site. The structural plans (foundations, columns, slabs) are drawn up by a structural engineer. The geotechnical study analyzes the soil in order to size the foundations, which is indispensable in clay or filled ground. Then come the technical plans (electrical, plumbing, ventilation, sanitation), the quantitative and cost estimate that prices the work item by item, and the descriptive note that fixes the materials, the finishes, and the technical standards.
The geotechnical study is often skipped. In the peripheral zones of Abidjan (Songon, Bingerville, Anyama), soils can be heterogeneous. A poorly sized foundation can produce structural cracks within a few years.
The building permit is governed by Loi n° 2019-576 portant Code de la Construction et de l'Habitat (Law 2019-576 on the Building and Housing Code). The file includes:
The file is submitted to the Guichet Unique du Permis de Construire (GUPC), the single window the MCLU set up to centralize applications.
Source: construction.gouv.ci, GUPC
| Element | Detail |
|---|---|
| Processing time | 1 to 3 months (varies by municipality and complexity) |
| Cost | Varies by area and municipality, generally between 100,000 and 500,000 FCFA |
| Validity | 3 years, work must begin within that period |
Watch the validity period. If work does not begin within 3 years, the permit lapses and you have to file a fresh application.
Five points to check before you sign. The MCLU technical accreditation, verifiable on construction.gouv.ci. References you can actually consult: completed sites, photographs, contact details of previous owners. A ten-year structural liability policy still in force, which protects against structural defects for 10 years. Enough financial capacity to hold the length of the project without asking for excessive advances. And a detailed quote, with a payment schedule tied to the stages of the work.
| Type | Principle | Risk for the owner |
|---|---|---|
| Fixed price | All-inclusive fixed price | Low, the price is firm |
| Quantitative estimate | Payment on the work actually done | Overrun possible |
| Turnkey | Architect and company, complete delivery | Low, but you depend on a single provider |
The fixed price is the most legible contract for a private individual. It gives visibility on the total budget from the moment you sign.
| Phase | Indicative duration | Description |
|---|---|---|
| Excavation and foundations | 2 to 4 weeks | Soil preparation, foundation pouring |
| Structural work | 2 to 4 months | Walls, columns, slabs, stairs |
| Framing and roofing | 2 to 4 weeks | Roof structure, covering |
| Second fix | 2 to 3 months | Electrical, plumbing, carpentry |
| Finishes | 1 to 2 months | Painting, tiling, fittings |
For a 150 m² villa, allow 8 to 14 months in total. Build in a 2 to 3 month buffer: delays are frequent, between supply, weather, and labor.
| Type | Cost per m² (excluding land) |
|---|---|
| Economy (standard concrete blocks) | 150,000 to 250,000 FCFA |
| Standard (common finishes) | 250,000 to 400,000 FCFA |
| High-end | 400,000 to 700,000 FCFA |
A standard 150 m² villa therefore comes to between 37.5 and 60 million FCFA (roughly 57,000 to 91,000 EUR), excluding the land and the architect's fees.
These figures are indicative. They vary with the location, the materials chosen, and market conditions.
At the end of the project, you (the owner) and the company carry out a handover inspection. A report is drawn up. It records compliance with the plans, the reservations, meaning the defects still to be corrected, and the deadlines for correcting them.
The company then has a set period to clear those reservations.
One year after the provisional handover, a second inspection confirms that every reservation has been cleared. That final handover starts the company's ten-year structural liability: 10 years on structural defects.
Once the construction is finished, ask the urban planning department of your municipality, or the MCLU, for the certificate of conformity. This document attests that your construction matches the permit that was issued.
Why it counts: without it, a formal resale or rental becomes complicated, banks ask for it before they will accept the property as security, and it proves your construction is legal if an inspection comes.
Official sources:
Further reading:
It is illegal. Constructions without a permit can be demolished by the administration, and you will not be able to obtain a certificate of conformity. Penalties are real and applied, particularly in zones undergoing regularization.
For a standard 150 m² villa, allow 8 to 14 months between the building permit and the handover of the works. Add 1 to 3 months for obtaining the permit itself.
An architect is mandatory above 150 m². Below that, one is recommended without being legally required. The building permit does call for technical plans that a private individual rarely produces alone.
Yes. The ACD is accepted as proof of ownership in the permit application, on the same footing as a registered Titre Foncier. The land must also sit in an approved subdivision.
No. Without an ACD or a Titre Foncier, no building permit will be issued. The village attestation does not constitute proof of ownership under urban land law.
Update 2025. Since 1 July 2024, the village attestation has been replaced by the ADU (Attestation de Droit d'Usage / customary land use certificate), and it has been issued free of charge since 1 January 2025 (Decree No. 2021-784).
It covers the defects and poor workmanship that compromise the soundness of the works or make them unfit for their intended purpose, for 10 years from the final handover. It does not cover cosmetic defects.
Capital Foncier verifies: title deed published, subdivision status checked, and state land status cross-referenced.

Grand-Bassam

Bingerville
20 / 20 lots available
TER-2026-UHMXE
Songon
5 / 5 lots available
TER-2026-N9DB4Widen your reading with other facets of Ivorian land.